"I have a question about the order of the construction process.
I believe it is step 3, you note that you have to order temporary electrical and port-o-toilet.
We are planning to be "off the grid" and use solar and wind with a battery storage system for our new home.
Do you suggest fully installing the wind/solar equipment first, or are there other alternatives for a temporary power source?
Thanks so much,
Marsha"
Hi Marsha,
You will need a generator!
Sun & wind power are not always available when you need a lot of electricity on demand.
Be sure to check that any generator you rent is adequate.
Undersized generators under heavy loads can cause a voltage drop resulting in an increase in current, damaging construction equipment.
Good luck,
Carl Heldmann, byoh.com